Project: Rapid exit taxiway “Y”
Year: 2018. – 2020.
Asphaltconcrete pavement: 11628 m2
Constructed equipment: Almost 18 km of ELT cables have been installed, with 71 lights embedded in the pavement. A 170-meter-long GRP rainwater drainage network has been constructed, equipped with a remotely controlled pump station system. Additionally, a 133-meter-long reinforced concrete/polymer concrete channel with F900 load class has been built. Drainage networks with a total length of 1.2 km have also been installed.