Project: Construction of Apron 5
Year: 2018. – 2020.
Concrete pavement: 36840 m2
Asphaltconcrete pavement: 14600 m2
Constructed equipment: Almost 16 km of ELT cables have been installed, along with a new transformer substation, 5 aircraft service pits (GPU), 5 A-VDGS units, 3 lighting masts, and 120 in-pavement MC lights. Additionally, 2 km of EST cables and 1 km of optical fiber cables have been installed, with 13 high-resolution video surveillance cameras. A 1.7 km water supply line has been constructed, including 6 fire hydrants. A 1.5 km GRP rainwater drainage network has been built with two treatment unit sets, as well as a 457-meter-long reinforced concrete/polymer concrete channel with F900 load class.